Solar carport installation, step by step

From site survey to handover: how a bolted solar carport goes up, what crew and equipment it needs, and how long it takes.

Solar carport installation, step by step

In short: after design approval and foundations, a bolted steel carport goes up bay by bay: columns, beams and braces, purlins, then modules and electrical. An experienced crew of 4–6 with a small crane typically erects 100–200 kWp of structure per week once the foundations have cured.

1. Survey and design

Measure the car park, mark existing drains, lights, trees and underground services, and take soil data. The layout, structural design and drawings follow, with the column grid fixed to the bay lines.

2. Foundations

Most carports stand on concrete pads or bored piers with anchor bolts cast in using steel templates, so every bolt group sits exactly where the column base plate needs it. On suitable soils, ground screws can replace concrete for lighter structures. Concrete needs time to cure before columns are loaded, usually about a week, depending on the mix and weather.

3. Columns

Columns are lifted onto the anchor bolts, levelled with nuts under the base plate, plumbed and tightened. Grout under the base plate follows once the line is aligned.

4. Beams and braces

Main beams are bolted to the column heads, and knee braces fitted. Check the line and level along the row before tightening fully.

5. Purlins and rails

Factory-punched purlins or module rails are bolted to the beams at the spacing on the drawing. On waterproof carports, gutter rails go in at this stage.

6. Modules and electrical

Modules are clamped row by row to the torque in the manual. Earthing, cable trays, inverters, lighting and chargers follow under the local electrical rules.

7. Checks and handover

Check bolt torques, earthing continuity and drainage; record coating damage and touch it up. Hand over drawings, test reports and the maintenance plan.

Equipment and crew

ItemTypical
Crew4–6 installers plus a supervisor
LiftingSmall mobile crane or telehandler for columns and beams
AccessMobile elevating work platforms for purlins and modules
ToolsTorque wrenches, levels, total station or laser for setting out

Working in a live car park

Close and fence one zone at a time, keep pedestrian routes open, and schedule lifts outside peak hours. Bay-by-bay part marking lets each zone be completed and reopened quickly.

See the structural design basics and our components.